Home / Asbestos Management Plan in Windsor: The Record a Building Owner Keeps

Asbestos Management Plan in Windsor: The Record a Building Owner Keeps

Reviewed November 2026 · Windsor & Essex County

Typical cost$200 – $600testing and survey only; the ongoing plan is the owner's to run
Results2–3 business daysrush available
Best forCommercial and institutional owners building the section 8 asbestos record

An asbestos management plan is the ongoing record a building owner keeps of where asbestos-containing material is in the building, what condition it is in, and what gets done about it over time. In Ontario it is not optional paperwork. Section 8 of O. Reg. 278/05 requires an owner who knows, or ought reasonably to know, that a building holds asbestos-containing material to run an asbestos management program: a written record, regular inspections, notice to the people who work in or on the building, and worker training. The plan runs for as long as the material stays in the building.

Every management plan starts from the same thing: knowing what is actually there. That is testing, and it is the one part we do. We are independent testers. We walk the building, sample every suspect material, send it to an accredited lab, and give you a report that says what is asbestos, where it is, and what condition it is in. That report is the foundation the record is built on. We do not remove, seal or enclose anything, and we do not run the plan for you, so the inventory we hand you has no abatement job riding on it.

Call (226) 773-8831 to scope a survey for your building, or send the form with the address, age and size.

Rather just talk?

(226) 773-8831

Answered 24/7. Tell us the material and the year the place was built, and you'll have a firm price on the call.

  • Testing and surveys only, never abatement
  • CALA-accredited lab, certificate included
  • Results in 2 to 3 business days
Call now

Something disturbed today? Call, don't wait.

Or send the details

We respond the same business day with a firm price.

No spam, no obligation. Your details go only to our Windsor team.

What the law actually requires

The owner's duties sit in two sections of O. Reg. 278/05, and it helps to keep them apart. Section 10 is the one-time duty before a project: determine whether asbestos is present, and hand that list to every bidder and contractor before demolition, alteration or repair. That is the designated substances survey world. Section 8 is the other half: the ongoing management of asbestos in a building that is simply being occupied and operated, with no project in sight. This page is about section 8.

The Ontario Ministry of Labour guide to the regulation states the owner's duties plainly. An asbestos management program is required in several situations, including when:

  • the owner of a building knows or ought reasonably to know, or has been told by an employer of workers in the building, that material used in the building is asbestos-containing;
  • the owner decides to treat a material as asbestos-containing;
  • an examination of the material determines, or would have determined, that it is asbestos-containing; or
  • a contractor or employer tells the owner about material that may be asbestos-containing and that was not in the pre-project report under subsection 10(4).

In a building old enough to hold suspect material, "ought reasonably to know" is a low bar. Windsor has the oldest housing and some of the oldest commercial and institutional stock in Ontario. The practical reading is that if your building predates the late 1980s and you have never had it surveyed, a survey is how you find out which duties you already carry.

What the plan has to contain

The Ministry guide lists what an asbestos management program must provide for. Read against a real building, it comes down to a record, a routine, and a set of notices.

Part of the plan What it means in practice
The asbestos record A document kept on the premises giving the location and condition of every asbestos-containing material, whether each is friable or non-friable, and for sprayed-on friable material the asbestos type or a statement it will be treated as a type other than chrysotile.
Inspections The material in the record is inspected at reasonable intervals to check its condition.
The 12-month update The record is updated at least once every 12 months, and whenever the owner learns new information about anything the record covers.
Written notice Occupiers, employers and workers get written notice of the information in the record that relates to the areas they work in or near.
Worker training A training program for workers whose work may involve or come close to the material: the hazards, protective equipment, personal hygiene, and the regulation's procedures.
Response to deterioration If material has fallen or is deteriorating, it is cleaned up, and the material is repaired, sealed, removed or permanently enclosed.

The record is the heart of it. An inventory that lists a material but not its condition, or that is two years old, is not a current record. The regulation names a specific clock: inspect, and update the record at least once in every 12-month period. That is the duty most owners miss, because the survey gets filed and then forgotten.

The point

A management plan is not a one-time document. It is a record you keep current while the asbestos is in the building, and a dated lab report is what each entry stands on.

The asbestos record, and why testing comes first

The record has to state whether each material is asbestos-containing and whether it is friable. Neither of those is a judgment you can make by looking. "Friable" has a precise meaning in the regulation: material that, when dry, can be crumbled, pulverized or powdered by hand pressure. Whether a material is asbestos-containing at all is a lab question, decided at the 0.5 per cent by dry weight line the regulation uses.

That is why a plan built on guesses is a plan built on sand. A ceiling texture logged as "assumed asbestos" costs you asbestos-rate handling on every future job touching it, even if it contains none. A pipe wrap logged as "non-friable" when it is actually crumbling is a worker-exposure problem and an enforcement one. A proper commercial asbestos testing survey settles both, material by material, and the lab sheet behind each entry is what an inspector, a contractor or a buyer's lawyer will ask to see.

For a single unit or a handful of materials, testing runs a few hundred dollars. A full building survey, which is what most management plans need at the start, is scoped by size, age and material count. We also analyze samples you or your own staff have already collected, if you want to seed the record before a full visit. Our guide to asbestos lab testing explains how that works and what the lab can and cannot tell you from a bag.

Inspections, notice and the people in the building

Once the record exists, the plan is about keeping it true and keeping people informed.

Inspection at reasonable intervals. The guide singles out sprayed-on insulation as the most significant source of airborne fibres, and lists what to look for: debris on horizontal surfaces, hanging material, dislodged chunks, scrapings, indentations, cracks, and any sign of water damage, since water dislodges and delaminates insulation. On pipe and boiler insulation, the protective jacket is the thing to watch, along with the unjacketed joints and elbows. None of that requires disturbing the material, and none of it is removal. It is looking, on a schedule, and writing down what you see.

Notice to occupiers. The owner gives occupiers written notice of any information in the record about the areas they occupy. An occupier who gets such a notice then has to tell their own workers and set up training for them. In a multi-tenant Windsor building, that chain is the owner's responsibility to start.

Notice to employers and workers. If the owner arranges work that is not a full section 10 project, say a contractor running network cable, and that work may involve or come close to material in the record, the owner must give that employer written notice. Workers the owner employs directly get the same information, plus the training program.

If a suspect material in a common area, mechanical room or ceiling space is found broken, crumbling or shedding, stop work in that area, keep people out, shut off any forced air that runs through it, and do not sweep or vacuum. Call before anyone disturbs it further.

When material is deteriorating: the four options, and the one we are not

The guide is explicit that a regular inspection program is how deteriorating asbestos insulation gets caught early. When material is established as asbestos-containing, or treated as if it were, and it is coming apart, the regulation gives the owner four control options: repair, seal, remove or permanently enclose.

  • Repair suits limited damage to pipe or boiler insulation, using non-asbestos plastering on open joints and areas around valves and flanges.
  • Sealing means spraying a sealant onto the material. On friable material that is a Type 3 operation under paragraph 2 of subsection 12(4), the highest-control class. Section 4(3) bars a liquid sealant where the material has visibly deteriorated or can no longer hold its own weight plus the sealant.
  • Removal takes the material out, classified by area and method.
  • Enclosure builds airtight walls and ceilings around the material.

Every one of those is abatement, and every one of them is a decision we have no stake in. We do not repair, seal, remove or enclose anything, and we do not sell any of it. What we do is tell you which materials are asbestos, whether they are friable, and what condition they are in, so that you, or the consultant who maintains your plan, can choose the right option and brief a contractor honestly. After a removal or an enclosure, an independent asbestos air test documents that the area is clear, and because we did not do the abatement, that result is genuinely independent.

Who carries this duty in Windsor

The ongoing-management duty is a building duty, not a homeowner one. Section 2(4) of O. Reg. 278/05 exempts the owner of a private residence that the owner or their family occupies, and the owner of a residential building of up to four units where the owner or their family lives in one of them. Above that line, the full owner side of the regulation applies.

In Windsor and Essex County that is a long list: landlords and property managers with the city's older rental stock, from Walkerville multiplexes to buildings near the University of Windsor; owners of offices, retail units, warehouses and industrial space; school boards, places of worship, and other institutional owners of mid-century buildings. If workers are in the building, asbestos management is an occupational health obligation rather than a suggestion. For most of these owners the sequence is the same: a survey to build the record, then the plan to keep it current. The survey is a commercial asbestos testing job, and where a building is heading into a renovation or demolition, the pre-project duty is a designated substances survey.

What testing for a management plan costs

We publish testing prices only. We do not charge to "manage" your plan, because the ongoing inspection, notice and training duties are the owner's to run; we provide the survey and the lab results the record is built from.

What is being tested Price
One material, for example a ceiling texture or a pipe wrap $200 to $350
Several materials in one visit $300 to $600
Full building survey $1,500 to $5,000 and up, scoped by size, age and material count
Lab analysis of a sample you already collected $50 to $100 per sample
Rush analysis adds 30 to 60 percent

Standard results take 2 to 3 business days. The report states asbestos content, condition and friability for each material, which is exactly the information the section 8 record has to carry. Our asbestos testing cost page breaks every tier down, and how long testing takes covers turnaround if you are working to a deadline.

Common questions

What is an asbestos management plan?

It is the ongoing record and routine a building owner keeps for asbestos-containing material: a written record of where it is and its condition, inspections at reasonable intervals, an update at least once every 12 months, written notice to occupiers, employers and workers, and worker training. Section 8 of O. Reg. 278/05 sets it out.

Is an asbestos management plan required by law in Ontario?

Yes, for buildings covered by the regulation. Section 8 requires an asbestos management program when an owner knows or ought reasonably to know that a building holds asbestos-containing material, when the owner chooses to treat material as asbestos-containing, or when an examination finds it. Owner-occupied private homes and small owner-occupied residential buildings of up to four units are exempt under section 2(4).

What must the asbestos record contain?

The location and condition of every asbestos-containing material, whether each material is friable or non-friable, and for sprayed-on friable material the type of asbestos or a statement that it will be treated as a type other than chrysotile. The record is kept on the premises.

How often does an asbestos management plan have to be updated?

The material in the record is inspected at reasonable intervals, and the record is updated at least once every 12 months and whenever the owner becomes aware of new information about anything it covers.

What is the difference between an asbestos management plan and a designated substances survey?

The survey is the one-time duty under section 10 and the Occupational Health and Safety Act before a renovation or demolition project, handed to every bidder. The management plan is the continuing duty under section 8 for a building that is simply occupied and operated. A building can need both: a survey to build the record, and a plan to keep it current.

Who needs an asbestos management plan in Windsor?

Owners of commercial, institutional and larger residential buildings that hold asbestos-containing material: landlords and property managers, offices and retail, warehouses and industrial space, schools and places of worship. Owner-occupied private homes are exempt.

Do you write or manage the plan for me?

No. We test and report only. We give you the survey and the lab results the record is built from, and we never remove, seal or enclose anything, so our inventory is independent of any abatement work. The ongoing inspections, notices and training are yours to run, or your consultant's.

Rather just talk?

(226) 773-8831

Answered 24/7. Tell us the material and the year the place was built, and you'll have a firm price on the call.

  • Testing and surveys only, never abatement
  • CALA-accredited lab, certificate included
  • Results in 2 to 3 business days
Call now

Something disturbed today? Call, don't wait.

Or send the details

We respond the same business day with a firm price.

No spam, no obligation. Your details go only to our Windsor team.

Ready for a straight answer?

Lab-verified results in 2 to 3 business days. Firm quote before we book anything.

Call (226) 773-8831
Call nowGet a quote